(914) 438-3705 angelogcontarctor@gmail.com 1133 Cortlandt St, Peekskill, NY 10566
Kitchen remodel project in progress in Westchester County NY with new cabinets and countertops
Kitchen Remodeling

How Long Does a Kitchen Remodel Actually Take From Start to Finish?

Angelo General Contractor Westchester County, NY 7 min read

Kitchen remodel timelines are one of the most common questions homeowners ask before committing to a project. The honest answer depends on the scope of work, but most quality kitchen remodels take six to twelve weeks from the start of demolition to final walk through. Adding planning, design, permits, and material lead times means the entire project typically runs four to seven months from initial consultation to completed kitchen.

Typical Kitchen Remodel Timeline
Design & Planning2 – 4 Weeks
Permits & Approvals2 – 6 Weeks
Cabinet Lead Time2 – 24 Weeks
Demolition & Rough In1 – 2 Weeks
Drywall, Cabinets & Finishes4 – 8 Weeks
Punch List & Final Inspection1 – 2 Weeks
Phase 01

Pre Construction Planning and Material Lead Times

The time before demolition begins often takes longer than the construction itself. Initial design and planning typically takes two to four weeks. Permit application and approval adds two to six weeks depending on the municipality. Cabinet ordering is usually the longest lead time item — stock cabinets arrive within two weeks, semi custom cabinets take six to ten weeks, and fully custom cabinets from specialty mills take ten to sixteen weeks. Countertop fabrication adds two to three weeks after templating. Smart planning means starting the design and ordering process months before you want demolition to begin.

Phase 02

Demolition and Rough In Construction Phase

Once construction starts, demolition takes one to three days for a standard kitchen. Larger kitchens or those involving wall removal take longer. Rough framing for structural changes adds two to four days. Plumbing rough in for new sink locations takes one to three days. Electrical rough in for new outlets, lighting, and appliance circuits takes two to four days. Building inspections happen at framing and rough in stages, requiring scheduling with the building department. This phase typically takes one to two weeks total and represents the messiest part of the project for homeowners living in the home during construction.

Phase 03

Drywall, Cabinets, Countertops, and Finishing

After rough in inspections pass, drywall hanging takes two to four days. Drywall taping and finishing adds five to eight days for level four standard finish. Painting before cabinet installation takes three to five days. Cabinet installation typically takes two to four days for a standard kitchen. Countertop templating happens after cabinets install, with fabrication taking another two to three weeks before installation. Backsplash tile installation takes two to four days. Final plumbing connections, electrical trim out, and appliance installation add two to four days. This phase represents most of the visible kitchen transformation.

Phase 04

Final Inspection and Post Construction Phase

Final building department inspection happens after all work completes, typically one to two days after notification. Punch list items including touch up paint, hardware adjustments, drawer alignment, and issues identified during walk through take two to five days to address. Final cleanup including construction dust removal and surface protection adds one to two days. The last week of any kitchen remodel addresses these details that distinguish quality finished work from rushed completion. Homeowners should expect the full construction phase to take six to twelve weeks total, with kitchen use limited until the final week when appliances connect and water service restores fully.

Free Consultation

Get Your Kitchen Remodel
Estimate in New York

Ready to start planning your kitchen remodel? Schedule a free in-home consultation with Angelo General Contractor today.